Where greater chennai corporation begins relaying roads

The greater Chennai company (GCC) will resume relaying approximately 2,200 roads in January and expects to complete the work in a month. The tender method turned into finished in advance, and the wait turned into for the monsoon to skip, said G.S Sameeran, Joint Commissioner (JC) (Works).

He said relaying paintings changed into no longer time-eating, and it might be undertaken across zones parallelly underneath more than one schemes.as soon as the rain absolutely subsides, we will begin relaying work. wherever there's milling required, it'll be completed. this could take kind of 10-15 days to be completed. apart from this, other areas may be done in a week,†he brought.

in step with Mr. Sameeran:we've many roads to restore in this economic year, so as to begin after January. inside the South location by myself, there are 600-seven hundred roads in a few areas that need relaying, and 300 in some different spots. We halted considering monsoon become drawing close, and new roads may not face up to the downpour.


consistent with the coverage word 2023-24 of the Municipal administration And Water deliver branch: “The town has 1,687 km of roads. in this direction, 211 km of roads were laid in the course of 2021-22 and 2022-23, and 171 km of roads has been proposed for relaying in 2023-24.â€

by using October eleven, as consistent with the organization, of the six bus route roads in zones 1, 2, 5, 10, 12, and 13, milling paintings has been done on  and relaying in 4, under the Tamil Nadu city avenue Infrastructure Fund (Turif) 2023-2024. similarly, of the 38 interior roads, 21 roads had been laid in coordination with the greater Chennai Police, underneath the Nagarpura Salai Mempattu Thittam (NSMT).

As of October 12, three,877 street works have been completed in regions beneath the GCC, said k.N. Nehru, Minister for Municipal administration, urban and Water Suppl, in a press convention previously.

Pothole restore
presently, the civic body is patching up roads across the town when they have been damaged in the course of the cyclone, Mr. Sameeran said.

in step with employer records, roughly 3,500 potholes of the 7,585 diagnosed in 3,109 roads were repaired as of December 22, and the ultimate could be completed in two weeks.